This page contains information regarding on-going construction
projects at Tinker Air Force Base. 

To get updates on the four-gate construction project, send an email to
the Team Tinker Construction Zone Team and put Opt-In in the subject line. 

Click here to see the complete list of gates and gate hours. Click here to see the Gott Gate Construction Zone.

updates

– CURRENT TRAFFIC ADVISORIES – 

Gate Closure: Truck Gate 33 (Air Depot at SE 59th St) until 30 Apr 2019 @ 1600 hrs (Contractor to install security enhancements at Truck Gate -  Piazza Gate will close on 14 Dec 2018 and reopen as the Temporary Truck (No POV's) on 17 Dec 2018) Leroy Boren

Parking Space Closure: Bldg. 469 Parking Lot EXTENDED until 22 Mar 2019 @ 1800 hrs (Contractor to trench 8 parking spaces on northwest corner and 3 parking spaces on southwest corner of Bldg. 469) Jane Moore Robinson

Parking Space Closure: Bldg. 416 South Parking Lot EXTENDED until 22 Mar 2019 @ 1800 hrs (Contractor to trench 12 parking spaces from Arnold to Building - Plates will be used over driving aisle) Jane Moore Robinson

Door Closure: Bldg. 9001 Entrance Door S22 EXTENDED to 28 Mar 2019 at 1700 hrs  (Contractor to replace Handicapped Entrance) [Tracking #19-038R] Larry Wakeman

Lane Closure:  SW Corner of Patrol Rd. & Hercules Rd. until 17 Apr 2019 at 1630 hrs (Nights & Weekends) (Contractor to widen the southwest corner of Patrol & Hercules turning radius) Jane Moore Robinson

Sporadic Lane Closures:  East Bound Lane on 5th St. between "F" Ave & "H" Ave until 31 May 2019 at 1600 hrs  (Contractor to excavate concrete over underground fuel tanks for generator at Bldg. 504 to replace) [Tracking #19-102] Sam Howard

Running Trail Closure:  Small section of Running Trail south of Bldg. 5606 on 18 Mar 2019 from 0700 hrs until 29 Jul 2019 at 1630 hrs (Contractor to replace asphalt) Jane Moore Robinson

– CONFIRMED UTILITY OUTAGES –  

Electrical Outage: Bldg. 215 REVISED to 30 Mar 2019 from 0700 hrs to 31 Mar 2019 at 1600 hrs (Contractor to run new conduit and wire to 2 Panels for HVAC System; Panel LA – 3 circuits and Panel RA – 21 circuits [Tracking #19-059R] Leroy Boren

Spring Maintenance Outage: Zone C (All facilities between Hruskocy Gate & Marauder Gate) on 5 Apr 2019 from 2330 hrs until 7 Apr 2019 at 2300 hrs (Semi-Annual Maintenance - ALL UTILITIESO&M REQUESTED [Tracking #19-068] Ko'be Galloway, Byron Morris, Jason Padgett, David Kirkpatrick

Spring Maintenance Outage: TAC Complex ( Bldg. 9001, 9201 & 9301) on 19 Apr 2018 from 2330 hrs until 21 Apr 2018 at 2330 hrs (Semi-Annual Maintenance - ALL UTILITIESO&M REQUESTED [Tracking #19-069] Ko'be Galloway, Byron Morris, Jason Padgett, David Kirkpatrick

Spring Maintenance Outage: NAVY COMPLEX (Bldg. 820, 821, 824, 825, 829, 830, 837, 838, 847, 848 & 851) on 19 Apr 2018 from 2330 hrs until 21 Apr 2018 at 2330 hrs (Maintenance on Cooling Tower and Compressors at Bldg. 821 and electrical systems throughout the complex) O&M REQUESTED [Tracking #19-078] Ko'be Galloway, David Kirkpatrick, Byron Morris 

Electrical Outage: Bldg. 4057 on 23 Mar 2019 from 0800 hrs to 1000 hrs (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-099] Mike Grimm 

Electrical Outage: Bldg. 4064 on 23 Mar 2019 from 1000 hrs to 1200 hrs (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-100] Mike Grimm 

Electrical Outage: Bldg. 4069 on 23 Mar 2019 from 1200 hrs to 1400 hrs (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-101] Mike Grimm

Electrical Outage: Bldg. 1122 on 30 Mar 2019 from 0800 hrs to 1000 hrs  (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-103] Mike Grimm 

Electrical Outage: Bldg. 1128 on 30 Mar 2019 from 1000 hrs to 1200 hrs (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-104] Mike Grimm 

Electrical Outage: Bldg. 1088 on 30 Mar 2019 from 1230 hrs to 1330 hrs (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-105] Mike Grimm

Electrical Outage: Bldg. 1095 on 30 Mar 2019 from 1330 hrs to 1530 hrs (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-106] Mike Grimm

Electrical Outage: Bldg. 5701 REVISED to 13 Apr 2019 from 0900 hrs to 1030 hrs (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-107] Mike Grimm

Electrical Outage: Bldg. 5702 REVISED to 13 Apr 2019 from 0700 hrs to 0900 hrs (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-108] Mike Grimm

Electrical Outage: Bldg. 5715 on 13 Apr 2019 from 1200 hrs to 1400 hrs (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-109] Mike Grimm

Electrical Outage: Bldg. 591 on 13 Apr 2019 from 1400 hrs to 1600 hrs (OG&E Contractor to install meter & CT's) OG&E REQUESTED [Tracking #19-110] Mike Grimm

Electrical Outage: Sub 5: To include 2102, 2110, 2111, 2112, 2113, 2119, 2121, 2122, 2136, 2210, 2211, 2280, 2283, 3120, 3202, 3209, 3212, 3213, 3120, 3220, 3221, 3225, 3228, 3234, 3334, 3507, 3604, 3610, 3703, 3705, 3706, 3707, 3708, 3714, 3715, 3805, 3812, 3902, 3904, 3907, 62503, 62508, 62509, 62514, 32515, 62516, 62525, 32527, 62528, 62540 and all Traffic Lights on East Dr. REVISED to 20 Apr 2019 from 0800 hrs to 21 Apr 2019 at 2000 hrs (OG&E to replace one section of bad UG cable from Circuit 31 at Sub 5) OG&E REQUESTED [Tracking #19-112R] Jason Berhardt

Electrical Outage: Sub 5: To include 2102, 2110, 2111, 2112, 2113, 2119, 2121, 2122, 2136, 2210, 2211, 2280, 2283, 3120, 3202, 3209, 3212, 3213, 3120, 3220, 3221, 3225, 3228, 3234, 3334, 3507, 3604, 3610, 3703, 3705, 3706, 3707, 3708, 3714, 3715, 3805, 3812, 3902, 3904, 3907, 62503, 62508, 62509, 62514, 32515, 62516, 62525, 32527, 62528, 62540 and all Traffic Lights on East Dr. on 6 Apr 2019 from 0800 hrs to 7 Apr 2019 at 2000 hrs (OG&E to replace the 1st section of bad UG cable from Circuit 31 at Sub 5) OG&E REQUESTED [Tracking #19-113] Jason Berhardt

Fire Sprinkler Outage: Bldg. 3001 (Col A-111 -Pratt Whitney) on 20 Mar 2019 from 0700 hrs to 21 Mar 2019 at 1700 hrs (Contractor to finish 6 runouts for new Steam Plant) HONEYWELL REQUESTED [Tracking #19-115] Jim Cartwright

Fire Sprinkler Outage: Bldg. 3105 until 7 Nov 2019 at 1330 hrs (Contractor to replace system and reconstruct main fire riser manifold) [Tracking #19-116] Larry Wakeman

Electrical Outage: Bldg. 3334 & 3705 on 23 Mar 2019 from 0800 hrs to 24 Mar at 1600 hrs (OG&E replace T-Bodies) OG&E REQUESTED [Tracking #19-123] Jason Bernhardt

Electrical Outage: 7017 (Entire Facility 1st 20 minutes) (SFS entire time) on 16 Mar 2019 from 0700 hrs to 1600 hrs (Alutiiq to replace a bad breaker & wiring between the breaker and transformer) ALUTIIQ REQUESTED [Tracking #19-124] Danny Fillmore

Electrical Outage: Bldg. 1, 13 & 23 on 30 Mar 2019 from 0800 hrs to 31 Mar 2019 at 1600 hrs (OG&E to remove t-taps and install new switchgear) OG&E REQUESTED [Tracking #19-126] Jason Bernhardt

Electrical Outage: Bldg. 3001 Admin (1AG-AJ77A to 1AG-AJ83A) on 23 Mar 2019 from 0700 hrs to 1100 hrs (Contractor to install 120V circuits from Panel's 1AH81A & 1AG81A for FM Directors Office) [Tracking #19-129] Winona Simmons

Water Outage: Bldg. 3902 REVISED to 24 Mar 2019 from 0700 hrs to  1600 hrs (User provided date) (Alutiiq to replace backflow preventer) O & M REQUESTED [Tracking #19-136] Jack Hasha  

– PROPOSED UTILITY OUTAGES – 

Electrical Outage: Bldg. 10, 11, 16, 18, 35 & 928 on 13 Apr 2019 from 0800 hrs to 14 Apr 2019 at 1600 hrs (OG&E to replace inoperable switchgear) OG&E REQUESTED [Tracking #19-127] Jason Bernhardt 

Electrical Outage: Bldg. 3113 on 27 Apr 2019 from 0800 hrs to 28 Apr 2019 at 2000 hrs (OG&E to pull wire in 3 manholes, install 6 sets of terminations & 5 sets of splices) OG&E REQUESTED [Tracking #19-130] Jason Bernhardt

Electrical Outage: Bldg. 3102, 3105 & 3113 on 4 May 2019 from 0800 hrs to 5 May 2019 at 2000 hrs (OG&E to pull wire in 4 manholes, install 2 sets of terminations & 6 sets of splices) OG&E REQUESTED [Tracking #19-131] Jason Bernhardt

Electrical Outage: Bldg. 10, 11, 16, 18, 35 & 928 on 11 May 2019 from 0800 hrs to 12 May 2019 at 1600 hrs (OG&E to replace failed cable & remove T-Bodies from 3 manholes) OG&E REQUESTED [Tracking #19-132] Jason Bernhardt 

Electrical Outage: Bldg. 590 & Eaker Gate on 18 May 2019 from 0800 hrs to 19 May 2019 at 1600 hrs (OG&E to install new switchgear & transformer and remove T-Bodies) OG&E REQUESTED [Tracking #19-133] Jason Bernhardt 

Natural Gas Outage: Zone A:  Bldg.'s 1, 3, 10, 11, 16, 18, 117, 200, 201, 202, 204, 210, 213, 214, 215, 216, 220, 229, 230, 240, 255, 260, 268, 282, 283, 284, 285, 289, 296, 400, 412, 413, 414, 416, 420, 469, 472, 477, 478, 506, 510, 590, 591, 685, 690, 801, 808, 810, 817, 819, 820, 824, 825, 827, 829, 830, 847, 848, 860, 861, 916, 930, 934, 935, 937, 943, 952, 961, 965, 976, 985, 986, 987, 989, 990, 994, 995, 998, 999, 1001, 1002, 1014, 1017, 1022, 1023, 1024, 1025, 1027, 1029, 1030, 1035, 1036, 1043, 1044, 1046, 1047, 1048, 1049, 1050, 1051, 1052, 1053, 1054, 1055, 1056, 1058, 1059, 1062, 1066, 1067, 1068, 1069, 1070, 1071, 1073, 1077, 1081, 1082, 1083, 1084, 1085, 1086, 1087, 1088, 1089, 1090, 1091, 1093, 1094, 1095, 1097, 1099, 1101, 1102, 1103, 1105, 1107, 1109, 1110, 1112, 1115, 1118, 1119, 1124, 1125, 1126, 1127, 1128, 1130, 1131, 1132, 1133, 1134, 1135, 1137, 1139, 1140, 1141, 1142, 1143, 1144, 1145, 1146, 1156, 1157, 1162, 1163, 5000, 5510, 5520, 5603, 5604, 5605, 5606, 5701, 5702, 5703, 5704, 5711, 5715, 5730, 5731, 5732, 5815, 5824, 5826, 5828, 5830, 5832, 5897, 5899, 5903, 5904, 5905, 5907, 5908, 5909, 5911, 5913, 5914, 5915, 5917, 5922, 5924, 5929, 5930, 5931, 5935, 5942, 5946, 5947, 6001, 6002, 6003, 6004, 6006, 6600, 6601, 6604, 6605, 6612, 6620, 6640, 6642, 7003, 7005, 7013, 7014, 7016, 7017, 7025, 7026, 7027, 7028, 7033, 7037, 7038, 7041 & 7042 on 27 Apr 2019 from 0700 to 28 Apr 2019 @ 1800hrs  (Contractor to tie into the main gas line at Arnold & Air Depot and Arnold & "E" Ave. Also tying in service lines to Bldg.'s 416, 469, 472 (Gas Station), 473 (Burger King), 478, 506, 510, 685 (BXTra) & 690 (Commissary). This outage will affect all facilities in Zone A) [Tracking #19-138] Jane Moore Robinson

traffic advisories


utility outages