This page contains information regarding on-going construction
projects at Tinker Air Force Base. 

To get updates on the four-gate construction project, send an email to
the Team Tinker Construction Zone Team and put Opt-In in the subject line. 

Click here to see the complete list of gates and gate hours. Click here to see the Gott Gate Construction Zone.

updates

 

Road & Partial Intersection Closure

Location: Arnold Ave. &  Air Depot Intersection

 

Duration: Multiphase construction project to start work on Monday, 7 Oct 2019 and end 31 Aug 2020 for road maintenance and repair near the intersection of Arnold Street and Air Depot Blvd south of the Tinker Gate.  Phase 1 begins 7 Oct 19 and ends 21 Dec 19 with the closure of two turn lanes on the westbound side of Arnold Street (see picture).  Please use caution when traveling through this area for worker safety.  Expect delays and plan your travel accordingly.

traffic advisories

CURRENT TRAFFIC ADVISORIES

Road Closure: Piazza Gate 31 & Midwest Blvd. from Munitions Rd. to SE 74th St. until 26 Apr 2020 at 0800 hrs (Contractor to install canopy, curb & gutter inside and outside the gate, install final denial barrier system, passive barriers and various lighting changes) Jane Moore Robinson/Inspector

utility outages

UTILITY OUTAGES

Electrical Outage: Bldg. 5701 revised again from 8:30 to 10 a.m. June 22 for OG&E contractor to install meter and CTs.

Electrical Outage: Bldg. 5702 revised again to 7 to 8:30 a.m. June 22 for OG&E contractor to install meter and CTs.

Electrical Outage: Bldg. 5715 revised to 10 to 11:30 a.m. June 22 for OG&E contractor to install meter and CTs.

Electrical Outage: Bldg. 3102, 3105 and 3113 revised to from 8 a.m. July 6 to 8 p.m. July 7 for OG&E to pull wire in four manholes, install two sets of terminations and six sets of splices.

Natural Gas Outage: Zone A: Bldgs. 1, 3, 10, 11, 16, 18, 117, 200, 201, 202, 204, 210, 213, 214, 215, 216, 220, 229, 230, 240, 255, 260, 268, 282, 283, 284, 285, 289, 296, 400, 412, 413, 414, 416, 420, 469, 472, 477, 478, 506, 510, 590, 591, 685, 690, 801, 808, 810, 817, 819, 820, 824, 825, 827, 829, 830, 847, 848, 860, 861, 916, 930, 934, 935, 937, 943, 952, 961, 965, 976, 985, 986, 987, 989, 990, 994, 995, 998, 999, 1001, 1002, 1014, 1017, 1022, 1023, 1024, 1025, 1027, 1029, 1030, 1035, 1036, 1043, 1044, 1046, 1047, 1048, 1049, 1050, 1051, 1052, 1053, 1054, 1055, 1056, 1058, 1059, 1062, 1066, 1067, 1068, 1069, 1070, 1071, 1073, 1077, 1081, 1082, 1083, 1084, 1085, 1086, 1087, 1088, 1089, 1090, 1091, 1093, 1094, 1095, 1097, 1099, 1101, 1102, 1103, 1105, 1107, 1109, 1110, 1112, 1115, 1118, 1119, 1124, 1125, 1126, 1127, 1128, 1130, 1131, 1132, 1133, 1134, 1135, 1137, 1139, 1140, 1141, 1142, 1143, 1144, 1145, 1146, 1156, 1157, 1162, 1163, 5000, 5510, 5520, 5603, 5604, 5605, 5606, 5701, 5702, 5703, 5704, 5711, 5715, 5730, 5731, 5732, 5815, 5824, 5826, 5828, 5830, 5832, 5897, 5899, 5903, 5904, 5905, 5907, 5908, 5909, 5911, 5913, 5914, 5915, 5917, 5922, 5924, 5929, 5930, 5931, 5935, 5942, 5946, 5947, 6001, 6002, 6003, 6004, 6006, 6600, 6601, 6604, 6605, 6612, 6620, 6640, 6642, 7003, 7005, 7013, 7014, 7016, 7017, 7025, 7026, 7027, 7028, 7033, 7037, 7038, 7041 and 7042 from 7 a.m. April 27 to 6 p.m. April 28 for contractor to tie into the main gas line at Arnold Ave. and Air Depot Blvd., and Arnold Ave. and E Ave. Also tying in service lines to Bldgs. 416, 469, 472 (gas station), 473 (Burger King), 478, 506, 510, 685 (BXTra) and 690 (Commissary). This outage will affect all facilities in Zone A.

Fire Sprinkler Outage: Bldg. 3105 until 1:30 p.m. Nov. 7 for contractor to replace system and reconstruct main fire riser manifold.